Xero purchase orders: creating them, turning them into bills, and what is still on order
How Xero purchase orders work: approval, creating a bill from a PO, part deliveries, why there is no open PO report, and a worked month-end list of open orders.
Updated 23 November 2026
ReportPilot reads your Xero and emails you what your numbers mean every Monday. Try it free (14 days, no card)
Short answer: a purchase order (PO) in Xero is a record of what you have agreed to buy from a supplier. It goes Draft → Awaiting Approval → Approved → Billed, and you can email it to the supplier as a PDF. A PO does not touch your accounts: nothing reaches the Profit and Loss, the Balance Sheet, Aged Payables or the GST or VAT return until you turn it into a bill. On an approved PO, Create bill copies the lines into a draft bill. You can lower the quantities to what actually arrived, and once every line has been billed Xero marks the PO as Billed. Xero has no report showing what is still to arrive or still to be billed on each PO. So at month end you build that list yourself: it tells you how much cash you have already promised to suppliers, and which goods arrived without a bill and need an accrual. The worked example shows both.
Menu names move between Xero releases and differ a little by region. If a label below does not match your screen, search for “purchase orders” in Xero’s menu.
How to create a purchase order in Xero
- Go to Purchase orders (under Business or Purchases, depending on your menu) and choose New purchase order.
- Pick the supplier, the order date and the delivery date. Xero gives the PO the next number in sequence. You can change the prefix and the next number in the purchase order settings, for example to PO-0001.
- Fill in the delivery address, the attention line and any delivery instructions. They print on the PO.
- Add the lines: an item if you use item codes (it fills in the description, the price and the account), the quantity, the unit price, the account the cost will go to and the tax rate. Choose whether the amounts are tax inclusive or exclusive. These codings carry over to the bill, so getting them right here saves recoding later.
- Attach the supplier’s quote if you have one, so whoever approves can see the agreed price.
- Save it as a draft, submit it for approval, or approve it straight away if your role allows. Then email it to the supplier or print it.
Templates. The PO’s look comes from the branding theme you pick on it (logo, layout, terms). Branding themes can use a custom Word (.docx) template, and purchase orders are one of the document types it covers, so a “Xero purchase order template” is a branding theme, not a separate setting.
Approval. Whether someone can create, approve, email or delete POs depends on their user role: the purchases permissions in Xero’s roles cover bills and purchase orders together. Xero has one level of approval, with no amount limits and no second approver. If you need “orders over £5,000 need the director”, that is a policy you enforce yourself, or a purchasing app from the Xero App Store. The Xero user roles guide shows what each role can see and do.
From purchase order to bill
When the supplier’s invoice arrives:
- Open the approved PO and choose Create bill. (Older Xero screens called this Copy to > Bill.)
- Xero fills in a draft bill with the PO’s lines at the full ordered quantities. Change each quantity to what the supplier actually delivered and invoiced.
- Enter the supplier’s invoice number as the bill reference, check the date and the amounts against their invoice, and approve the bill.
The bill is what posts the cost and the GST or VAT, and puts the amount in Aged Payables. If you use tracked inventory items, the quantity on hand also changes when the bill is approved, not when the PO is approved or when the goods arrive. The Xero inventory report guide explains why that date matters.
Part deliveries (“part billed”). If only some of the order came, bill only what came. The PO stays Approved, and you create another bill from it when the rest arrives. Once every line is fully billed, Xero marks the PO Billed. Four things trip people up:
- The PO’s total does not go down. Xero shows what has been billed against each line, but not the money left to bill. The PO list still shows the full order value.
- Deleting a draft bill made from a PO may not give the quantities back to the PO, according to users reporting this to Xero. Check the PO before you create the bill again.
- To bill a PO that is already marked Billed (a late extra delivery, or a bill made in error), use Unmark as billed from the PO’s options menu, then create the bill.
- Bills that arrive another way are not linked. A supplier invoice that comes in through Hubdoc, Xero’s email-in address or a bank feed match is a separate bill with no link to the PO. Mark the PO as Billed by hand, or it sits in your open orders for ever and inflates what you think is still on order.
Is there a purchase order report in Xero?
Not one that answers “what is still on order”. What there is:
| Where | What it shows | What it does not |
|---|---|---|
| The Purchase orders list, Approved tab | Every open PO with supplier, dates and total | What is left on each PO after a part bill |
| A single PO | Ordered and billed quantities per line | Anything across several POs |
| Payable Invoice Summary | Bills per supplier; Xero staff say it can also show purchase orders by contact | The open balance per PO |
| Profit and Loss, Balance Sheet, Aged Payables | Nothing from POs at all | Committed spend |
Xero’s own feature-request board has long-running requests for an outstanding PO report and for showing part-billed amounts. They are still open, so until that changes the month-end list below is a short manual job. Firms with dozens of open orders a month usually use a purchasing or inventory app that keeps the open balance.
A worked example: what’s still on order at month end
These figures are made up. Oakline Joinery Ltd makes kitchens and fitted furniture in Bristol, is VAT-registered and orders all its timber and materials on Xero POs. Materials post to Cost of sales: Materials; it does not use tracked inventory. On 31 October the Approved tab shows five open POs. Amounts are in pounds, excluding VAT.
Step 1: list the open POs, and what arrived and was billed on each.
| PO | Supplier | What | PO total | Received by 31 Oct | Billed | Received, not billed | Still to arrive |
|---|---|---|---|---|---|---|---|
| PO-0409 | Timberline Ltd | 60 sheets birch ply at £52 | 3,120 | 30 sheets | 1,560 | 0 | 1,560 |
| PO-0412 | Timberline Ltd | 40 oak boards at £85 | 3,400 | 24 boards | 0 | 2,040 | 1,360 |
| PO-0415 | Fixings Direct | Hinges and handles | 640 | All | 0 | 640 | 0 |
| PO-0418 | Coatings UK | 12 tins of lacquer at £45 | 540 | None | 0 | 0 | 540 |
| PO-0420 | Hardwood Imports | Walnut slabs | 6,200 | None | 0 | 0 | 6,200 |
| Total | 13,900 | 1,560 | 2,680 | 9,660 |
The “received” column comes from the delivery notes in the workshop, not from Xero: Xero has no goods-received step.
Step 2: what is really still owed on these orders. The Approved tab adds up to £13,900, but £1,560 of PO-0409 was billed on 15 October and is already in the books. What is left is £13,900 − £1,560 = £12,340. That is £2,680 of goods that arrived without a bill, plus £9,660 not yet delivered.
Step 3: the accrual for goods received, not billed. The oak boards and the fixings are in the workshop, and some are already in kitchens invoiced in October, but no bill has come. Without an accrual, October’s materials are £2,680 too low. Post a manual journal dated 31 October: debit Cost of sales: Materials £2,680, credit Accruals £2,680, no VAT (the VAT comes in with the bills). Set it to reverse on 1 November, so the bills, when they arrive, land against it. The accruals in Xero guide has the steps.
It matters to the margin. October’s sales were £48,000 and recorded materials £17,520, a gross margin of (£48,000 − £17,520) ÷ £48,000 = 63.5%. With the accrual, materials are £20,200 and the margin is (£48,000 − £20,200) ÷ £48,000 = 57.9%. The 63.5% was not a good month. It was a bill that had not arrived yet.
Step 4: the cash already promised. The £12,340 still owed on the POs will cost £12,340 × 1.2 = £14,808 with VAT. The VAT is reclaimed later, but it is paid to the supplier first. Oakline has £21,500 in the bank and £8,900 of bills (including VAT) in Aged Payables. Bills alone leave £21,500 − £8,900 = £12,600. The orders take that to £12,600 − £14,808 = −£2,208. None of the £14,808 appears in Xero’s reports or its short-term cash flow, because POs are not transactions. So the bank balance looked comfortable while the business had already promised £2,208 more than it held. That is fine if customers pay on time, but it is the reason to look before approving the next big order, not after. The Xero short-term cash flow guide covers the bills-and-invoices side of the same question.
Step 5: tidy the list. PO-0415 has been fully received. When Fixings Direct’s invoice arrives through Hubdoc, it will not be linked to the PO, so whoever enters it should mark PO-0415 as Billed. Otherwise next month’s list will show £640 still on order.
Purchase order, bill or quote?
| Purchase order | Bill | Quote | |
|---|---|---|---|
| Who issues it | You, to a supplier | The supplier, to you (you enter it) | You, to a customer |
| Changes your accounts | No | Yes: cost, GST or VAT, Aged Payables | No |
| Approval | Draft → Awaiting Approval → Approved | Optional approval before it posts | Sent → Accepted or Declined |
| Becomes | A bill, via Create bill | Paid, from the bank | An invoice |
A customer’s purchase order is different again: it is their PO to you. Put their PO number in the Reference of your invoice so it prints on it. Many customers will not pay an invoice without it.
A monthly check for purchase orders
- Open the Approved tab and look at anything with a delivery date more than a month ago. It is either late (chase the supplier) or already billed some other way (mark it Billed).
- For part-billed POs, work out what is left from the billed quantities, not the PO total.
- List goods received but not billed and accrue them at month end (step 3 above).
- Add up what is still to arrive, with VAT or GST, and compare it with the bank balance after bills (step 4 above).
- Clear out old drafts and anything awaiting approval that will never be approved.
The Xero month-end checklist has the rest of the month-end routine, and the supplier report guide shows what you spent with each supplier once the bills are in.
Common questions
Does Xero do purchase orders? Yes. Purchase orders are built into Xero: you create, approve, email and print them, then create a bill from them when the supplier’s invoice arrives. There is one level of approval, no goods-received step and no report of open balances.
How do I turn a purchase order into a bill in Xero? Open the approved purchase order and choose Create bill (Copy to > Bill on older screens). Xero fills in a draft bill with the order’s lines. Change the quantities to what was delivered, add the supplier’s invoice number and approve it.
Can a purchase order be part billed in Xero? Yes. On Create bill, lower the quantities to what arrived. The purchase order stays approved and you bill the rest later. Xero marks it Billed only when every line is fully billed, and it does not show the money left to bill, so work that out from the billed quantities.
Do purchase orders affect my accounts in Xero? No. A purchase order does not post to the Profit and Loss, the Balance Sheet, Aged Payables or the GST or VAT return. Only the bill does. Goods that have arrived without a bill at month end need an accrual.
Is there an outstanding purchase orders report in Xero? Not with the open balance on each order. The Approved tab of the purchase orders list shows every open order at its full value. For what is really still on order, subtract what has been billed on each, as in the worked example.
How do I set up approval for purchase orders in Xero? Give the people who should approve a user role that can approve purchases, and have everyone else submit orders for approval. Xero has one approval step with no amount limits; multi-level approval needs an app.
Can I change a purchase order after it is approved? Yes, until it is billed you can edit it and send the supplier the updated version. Once it is billed, change the bill instead.
Your bills and cash, watched for you every Monday
ReportPilot reads your Xero figures and sends a short plain-English email every Monday: sales, costs and profit against last month and the same month last year, the cash in the bank, and bills due against that cash. It reads bills, not purchase orders. So it is the bills from your orders, as they arrive, that show up there, along with a margin that looks too good because a bill is missing. It asks Xero for read-only access, and there is a 14-day free trial with no card.
No Xero needed
Get a sample Monday email for a business like yours
Pick your kind of business, rough sales and country. We email you the Monday email ReportPilot would write for a business like that: cash, sales and profit against last month, who owes money and one thing to do. Made-up figures, clearly labelled as a sample, from the same engine as the real one.
We email a link to confirm first; nothing else is sent until you press it. Then the sample, a few related emails over three weeks and a monthly cash check. One click to unsubscribe.
No need to wait for the email: read your sample now.